We closed our temporary Chicopee location and reopened in the new Springfield store on Monday, June 26th, 2000.

new building

Our new facility at 274 Taylor Street is only a block away from our former Springfield home on Worthington Street.

Due to our devastating fire in July of 1998, we had the opportunity to build a new state-of-the-art facility (designed by Associated Builders, Inc) for our main branch in Springfield.

June, 2000. The building is complete.

Picture of Store

Click on any of the pictures with a border to see a larger version.

May 2, 2000. Power to the building.

                           

April 7, 2000. Progress on the front canopy and a closeup of the craftmanship that's being put into this proud inanimate object!

canopy     canopy    

March 31, 2000. As the outside of the building is buttoned up, work inside is progressing.

outside    

March 23, 2000. The bricks are climbing up the front facade and the floor under the second floor has been poured.

facade    

March 8, 2000. And the roof goes on...

roof     roof    

March 2, 2000. You can get a real sense of what the building is going to look like.

Outside walls     Interior    

February 29, 2000. The windows are being framed in so that the rest of the outer shell can be installed.

Window framing     Window framing    

February 24, 2000. The outside skin is going up.

One side skinned     The back is skinned    

February 15, 2000. The front canopy is now in place.

The canopy     The canopy     The canopy The canopy

February 7, 2000. The framework is going up very quickly.

The framework     The framework     The framework

February 3, 2000. The roof girders are now in place.

The roof     The roof

February 1, 2000. The building starts taking shape as the sides are raised. Here's to the future home of Hampden/Zimmerman Electric Supply!

The back is up     The corner pieces are attached

January 28, 2000. The back is up and the corner pieces are being attached to the front. Wind chill is -17 degrees today.

The back is up     The corner pieces are attached

January 27, 2000. Things are moving again at last. The steel has been delivered and the front of the building is rising from the snow.

The front girders go up     The front girders go up     The front girders go up

The site work:

The cement trucks arrive December 21, 1999

Site work December 14, 1999

Site work December 13, 1999

Site work November 30, 1999

Site work November 30, 1999

Site work November 22, 1999

Site work November 22, 1999

The Fire at Hampden/Zimmerman